Purchasing Card Lead-timeProject Description:Problem Statement: From January to March firm lost 28 days availability (from 35 days to 7 days) on 80% of employee purchasing cards requested. This 28-day loss of electronic purchasing requires the substitution of manual invoice processing and a loss of interchange revenue opportunities. Goal Statement: By October, reduce the lead time for issuing employee purchasing cards from 35 days to 7 days and reduce the volume of requests by 80%. Start Date: May End Date: December Project Metrics
DPMO: Measure: 1,000,000 Control: 10,000 Project BenefitsDirect Savings:$17,000
Soft Savings:$245,000
Realized Savings: $262,00 Project Accomplishments
|
||||||||||||||||||||||||